This policy sets forth the process for which change orders will be submitted for approval.
A Change Order is the written mechanism to revise a contract between the District and a contractor working for the District. If it is determined that a change to the contract is necessary, the Districts architect will prepare a Request for Proposal (RFP) document and after approval by the District, will issue it to the contractor. The contractor will respond to the RFP with a proposal indicating cost and time impact to the project. If both the architect and District agree with the cost and time impact, the architect prepares a Construction Change Directive (CCD). This is a tracked document that indicates that both parties agree to the time and cost impact. The Districts approval of the CCD will be determined by the following:
In order to be considered for approval, all CCDs must meet the following requirements:
A collection of CCDs are then grouped to form a Change Order. The Change Order is the official record of the RFPs and CCDs and is processed as a Board of Trustee action item and is also part of the project record for Notice of Completion and DSA approval and closeout.
WKCCD Board Policies & Procedures
Approved 2/9/05
|
Chapter 6 Policies Board Policies & Procedures Home |
Taft
College 2002 |